| Project Title: |
Ringrose Slope Hydrology Project |
| Project Number: |
EP pending - Ringrose |
|
| District: |
Arrow Boundary Forest District |
|
| Location: |
Slocan Valley, South of Slocan City
Lat. 49 45'N Long. 117 28'W to
Lat. 49 43'N Long. 117 27'W |
|
| Principal Researcher: |
David Toews
Forest Sciences Section
Southern Interior Forest Region |
Phone:
(250) 825-1100
e-mail:
David.Gluns@gov.bc.ca |
|
|
|
Objectives:
-
To establish relationships between snowpack water equivalents during snow
accumulation and melt periods on slopes above Thickett Creek, Gurn Brook
and Gurn Spring and to determine how these relationships are changed following
logging;
-
To establish relationships between discharges during high flows and low flows
on Thickett Creek, Gurn Brook and Gurn Spring to determine whether these
relationships are changed following logging;
-
To establish relationships between snow ablation and discharge during high
flows to determine whether these relationships are changed following logging;
-
Two additional secondary objectives were also included in the original study
plan;
-
To determine short-term impacts of new road construction on sediment levels;
and
-
To document any seepage interception and diversion resulting from new road
construction.
Experimental Design:
-
This paired watershed study uses very small streams. The catchment area of
the watersheds do not have distinct boundaries. Measurements include monitoring
of the three streams to determine water quantity and timing. Additionally
the snowpack is measured on two transects at different elevations in the
drainage area of the streams.
-
The analysis approach is the time series technique. It is an analysis technique
that allows us to analyze the fine structure of a hydrological time series
and determine the effects of intervention on that time series.
History:
The study was initiated in 1986. Treatment can take place at any time, however,
harvesting has been delayed due to opposition by local water users. Data
collection, in cooperation with Slocan Forest Products, has continued
annually to 2001. In addition, piezometers were installed in 2001 throughout
the watershed.
Status: Active
Reports and Publications:
Salway, A.A. 1993. Time series analysis of discharge and snow water equivalent
data. Thickett Slope, 1988-1992, Calibration Phase. Unpubl. Progress Report.
B.C. Min. For., Nelson, B.C.
Salway, A.A. 1988. Ringrose slope - Hydrological research project. 1986-1988.
Unpubl. Progress Report. B.C. Min. For., Nelson, B.C.
Toews, D. and Mike Curran., 1992. A review of planning procedures and water
protection issues for Ringrose slope. Unpublished report, Ministry of Forests,
Nelson, 22 pages.
|