Forest Practices Code of British Columbia Act
if you are still required to comply with this Act, that is you are currently operating under an existing development plan, then you must abide by the following:
Forest Road Regulation
Notice required for construction modification
20
(1) 20 (1) In this section, “commencement” means initial commencement or re-commencement after an inactive period of 3 months or more.
(2) A holder of an agreement under the Forest Act must notify the district manager, in accordance with subsection (3), before commencement of road construction or modification to relocate a road.
(3) A notice under subsection (2) must specify
(a) the location, including any administrative identifier that pertains to the location;
(b) the holder of the agreement under the Forest Act,
(c) the name of the holder’s representative who is responsible
for conducting the road construction or modification;
(d) the projected date for commencement.
(4) The district manager may exempt a holder of an agreement under the Forest Act, conditionally or unconditionally, from the requirements of subsection (2).
(5) A holder of an agreement under the Forest Act who is exempted under subsection (4) must comply with any of
the conditions specified in the exemption.
July 2003 (B.C. Reg. 292/03) effective August 5, 2003; December 2003 (B.C. Reg. 466/03)