BCBID Contract
EN10V8G014
Questions and Answers
Invitation to Tender
Lillooet West Forest Service Road
- 36km Road Realignment
Closing Date and Time:
September 21, 2009 15:00hrs
36 km Road Realignment Site Meeting: 2009-09-15
Issues discussed:
·
Review of
staking.
·
Construction
expectations (running width 8 m unless otherwise specified,
grubbed/keyed in/compacted fill slope is expected, ½ meter ditch).
·
“Knock-outs”
for hydro poles are to be grubbed out as per the design drawings.
·
Traffic –
Ministry of Forests and Range will look into complete closures; at
this point, assume status quo with flagging and minor road delays
(less than half an hour). It
is the successful contractor’s responsibility to consult with and
communicate an acceptable closure plan to the local communities and
road users.
·
30 cm of good
“gradeable” material is expected to be spread over the entire length
of road realignment.
·
Capping
material can be developed from the Billygoat pit, from the southern
end of the current opening in the forest service road right-of-way.
Questions and Answers:
Q
What to do with Debris?
A Debris
from this road realignment and pit development is to be piled for
burning at a later date at the end of the 0+550 spur or at the
Billygoat pit. These
piles cannot be located underneath the power line and must be a
minimum of five meters from adjacent timber.
Q
What slope markers are to be
used at station 0+460?
A
At station 0+460, upper blue line indicates
the anticipated top of cut/bank (not the lower blue line).
Q
Who will be doing the
centreline staking and when will it be done?
A
Centreline of road layout will
be staked by Hedberg and Associates prior to construction.
|